UNIT-1
1.What
is planning?
Planning aims at
formulation of a time based plan of action for coordinating various activities
and resources to achieve specified objectives. Planning is the process of
developing the project plan. The plan outlines how the project is to be
directed to achieve the assigned goals. It specifies a predetermined and
committed future course of action, based on discussions and decisions made on
the current knowledge and estimation of future trends.
2.What
is construction planning?
The construction
planning process is stimulated through a study of project documents. These
documents include but are not limited to
the available technical and commercial studies and investigations, designs and
drawings, estimation of quantities,construction method statements, project
planning data, contract documents, site conditions, market survey, local
resources, project environment and the client’s organization. The planning
process takes in to account, the strengths and weakness of the
organizations.
3.What
are the objectives of planning?
Proper design of each element of the
project
Proper selection of equipment and
machinery in big projects, the use of large capacity plants are found
economical
Procurement of materials well in
advance
Proper arrangement of repair of equipment
and machinery
Employment of trained and experienced
staff on the project
To provide incentive for good workers
To arrange constant flow of funds for the
completion of project
To provide proper safety measures and
ventilation, proper arrangement of light and water.
4.What
are the types of project plans?
Planning the entire
project from its inception to completion requires a vast coverage, varied
skills and different types of plans. The nature of plans encountered in a
typical construction project are indicated below
Types
of project plans
Development stage
nature of plan
Inception stage project feasibility plan
Engineering stage
project preliminary plan
Implementation
stage
project construction plan
5.Define
work tasks?
Work tasks represent
the necessary frame work to permit scheduling of construction activities, along
with estimating the resources required by the individual work tasks and a
necessary precedence or required sequence among the tasks. The terms work tasks
or activities are often used interchangeably in construction plans to refer to
specific defined items of work.
6.List
out the project planning techniques?
Stages
|
Planning
process
|
Techniques/methods
|
1.
Planning time
|
1.Breaking
down project work,
developing
time network plans.
|
1.Work
break down, network analysis,gnat chart.
|
2.
Planning resources
|
2.
Forecasting resource requirements,
planning
manpower requirements,
planning
material requirements,
budgeting
costs, designing
organizational
structure.
|
2.
Man power scheduling Material
scheduling
Resource allocation Cost
planning
& budgeting Equipment
selection
and scheduling.
|
3.
Planning implementation
|
3.Formulating
monitoring methodology
|
3.
Resource productivity control,time control, contribution control, budgetary
control .
|
7.What
are the steps involved in planning?
a.defining the scope
of work to be performed
b.preparing the logic
or network diagram to establish a relationship among activities and integrating
these diagrams to develop the network model
c.analyzing the
project network or models to determine project duration, and identifying
critical and non-critical activities
d.Exploring trade-off between time to cost to
arrive at optimal time and costs for completing the project.
e. Establishing
standards for planning and controlling men, materials, equipment, costs and
income of each work package
f. Forecasting input
resources, production costs and the value of the work done
g. Forecasting the
project budget allocations for achieving targets assigned to each
organizational unit
h. Designing a control system for the
organization
i. Developing the resources, time and cost
control methodology
8.
What is the purpose of coding?
a. To identify the
data connected with each work package, as work packages from the database for
managing various project functions.
b. To aid in the organization of data from the
very detailed to the very broad levels
c. To enable the
processing, sorting, and extraction of information required at various levels
of management and functional units.
d. To computerize the
data processing system
9.
How many categories available in codification?
In construction
projects, the codes used can be broadly divided in to two categories i.e.
project interfacing codes or simply referred as project codes and department
specialized codes.
Project interface
codes:
These are the common
codes used for developing an inter department database. Ex: a project code for
the foundation of a building.
Departmental
specified codes:
These codes are
developed by the departmental heads for their use. Ex: to indicate the location of materials
in site ware houses
10.
Define the types of labeling approach?
a. alphabet codes
b. numerical
codes
c. alphanumeric codes
Alphabet
codes:
Alphabet letters A to Z, single or combined,
can be used to represent a code. An alphabet in a single character space can
represent 26 variations as compared to numerals 0 to 9, which can depict
maximum of 10 variations
Numerical
codes:
It is the most important form of coding in
numerical codes, each character can be represented by a numerical varying from
0 to 9
Alpha
numerical codes:
It is the combination of alphabets and
numerals to develop a each code.
11.
Defining precedence relationship among activities?
Precedence relations
between activities signify that the activities must take place in a particular
sequence.
Numerous natural
sequences exist for construction activities due to requirements for structural
integrity, regulations and other
technical requirements.
For example
Excavate place formwork place reinforcement pour concrete Trench
12.Define
the following terms?
i.activity
ii.event
Activity: A project
can be broken down in to various operations and process necessary for its
completion. Each of these operations and
processes, which consume time and possibly resources, is called activity. The
activities are represented by
arrows.
For example:
Excavation
2
Event: It is the state
between the completion of a preceding activity and the beginning of the
succeeding one. It has no duration an event is shown by a circle or ellipse
1
2
13.
Define activity direct cost?
This is the cost that can be traced in full
with the execution of a specific activity. It consists of costs of direct
labour,direct equipment and other direct costs. For example: in the activity of
roof concreting, the following direct costs would be involved.
Types of costs item of costs
Direct materials cost of concrete and steel
Direct labour cost of labour employed
14.
Define activity indirect cost?
This is the cost that
incurred while performing an activity, but cannot be traced directly to its
execution. In other words, all costs other than the direct ones fall in this
category. These represent the apportioned share of supervision general and
administration costs are commonly refer to as overheads.
16
MARK QUESTIONS
1. What is Construction Planning? Explain the
basic concepts in the development of Construction plans. Construction planning is a
fundamental and challenging activity in the management and execution of
construction projects. It involves the
choice of technology, the definition of work tasks, the estimation of the
required resources and durations for
individual tasks, and the identification of any interactions among the
different work tasks. A good construction
plan is the basis for developing the budget and the schedule for work.
Developing the construction plan is a critical task in the management of construction, even if the
plan is not written or otherwise formally recorded. In addition to these technical aspects of construction planning,
it may also be necessary to make organizational decisions about the
relationships between project
participants and even which organizations to include in a project. For example,
the extent to which sub-contractors will be used on a project is often
determined during construction planning.
A planner begins with a result (i.e. a
facility design) and must synthesize the steps required to yield this result.
Essential aspects of construction planning include the generation of required
activities, analysis of the implications of these activities, and choice among the various alternative
means of performing activities. In contrast to a detective discovering a single
train of events, however, construction
planners also face the normative problem of choosing the best among
numerous alternative plans. A planner
must imagine the final facility as described in the plans and specifications.
In developing a
construction plan, it is common to adopt a primary emphasis on either cost
control or on schedule control. Some
projects are primarily divided into expense categories with associated costs.
In these cases, construction planning is
cost or expense oriented. Within the categories of expenditure, a distinction is
made between costs incurred directly in
the performance of an activity and indirectly for the accomplishment of the project.
For example, borrowing expenses for
project financing and overhead items are commonly treated as indirect costs.
For other projects, scheduling of work
activities over time is critical and is emphasized in the planning process. In
this case, the planner insures that the proper
precedences among activities are maintained and that efficient scheduling of
the available resources prevails.
Traditional scheduling
procedures emphasize the maintenance of task precedences (resulting in critical
path scheduling procedures) or efficient
use of resources over time (resulting in job shop scheduling procedures).
Finally, most complex projects require consideration of both cost and
scheduling over time, so that planning, monitoring and record keeping must consider both dimensions. In these cases, the
integration of schedule and budget information is a major concern.
Alternative
Emphases in Construction Planning
Construction planning
is not an activity which is restricted to the period after the award of a
contract for construction.It should be an essential activity during the
facility design. Also, if problems arise during construction, re-planning is required.
2. Explain briefly Choice of Construction
Technology and Construction method?
Choice of Construction Technology and
Construction method
As in the development of appropriate
alternatives for facility design, choices of appropriate technology and
methods for construction are often
ill-structured yet critical ingredients in the success of the project. For
example, a decision whether to pump or
to transport concrete in buckets will directly affect the cost and duration of
tasks involved in building construction.
A decision between these two alternatives should consider the relative costs,
reliabilities, and availability of equipment
for the two transport methods. Unfortunately, the exact implications of
different methods depend upon numerous
considerations for which information may be sketchy during the planning phase,
such as the experience and expertise of
workers or the particular underground condition at a site.
In selecting among
alternative methods and technologies, it may be necessary to formulate a number
of construction plans based on
alternative methods or assumptions. Once the full plan is available, then the
cost, time and reliability impacts of
the alternative approaches can be reviewed. This examination of several
alternatives is often made explicit in bidding
competitions in which several alternative designs may be proposed or
value engineering for alternative construction
methods may be permitted. In this case, potential constructors may wish
to prepare plans for each alternative design using the suggested construction method as well as
to prepare plans for alternative construction methods which would be proposed as part of the value engineering
process.
In forming a
construction plan, a useful approach is to simulate the construction process
either in the imagination of the planner
or with a formal computer based simulation technique. By observing the result,
comparisons among different plans or
problems with the existing plan can be identified. For example, a decision to
use a particular piece of equipment for an
operation immediately leads to the question of whether or not there is
sufficient access space for the equipment. Three dimensional geometric models in a computer
aided design (CAD) system may be helpful in simulating space requirements for operations and for identifying any
interferences. Similarly, problems in resource availability identified during
the Construction planning Direst cost
Indirect cost Time oriented
(critical path problem) Resource oriented(job schop schedule) Schedule oriented
Cost oriented simulation of the construction process might be effectively
forestalled by providing additional resources as part of the construction
plan.
Example-
Laser Leveling
An example of technology choice is the use of
laser leveling equipment to improve the productivity of excavation and grading. In these systems, laser surveying
equipment is erected on a site so that the relative height of mobile equipment
is known exactly. This height
measurement is accomplished by flashing a rotating laser light on a level plane
across the construction site and
observing exactly where the light shines on receptors on mobile equipment such
as graders. Since laser light does not
disperse appreciably, the height at which the laser shines anywhere on the
construction site gives an accurate indication
of the height of a receptor on a piece of mobile equipment. In turn, the
receptor height can be used to measure the
height of a blade, excavator bucket or other piece of equipment. Combined with
electro-hydraulic control systems mounted
on mobile equipment such as bulldozers, graders and scrapers, the height of
excavation and grading blades can be precisely
and automatically controlled in these systems. This automation of blade heights
has reduced costs in some cases by over
80% and improved quality in the finished product, as measured by the desired
amount of excavation or the extent to which
a final grade achieves the desired angle. These systems also permit the use of
smaller machines and less skilled operators.
However, the use of these semi-automated systems require investments in the laser
surveying equipment as well as
modification to equipment to permit electronic feedback control units. Still,
laser leveling appears to be an excellent
technological choice in many instances.
3. Explain coding systems
One objective in many
construction planning efforts is to define the plan within the constraints of a
universal coding system for identifying activities. Each activity defined for a
project would be identified by a pre-defined code specific to that
activity. The use of a
common nomenclature or identification system is basically motivated by the
desire for better integration of organizational efforts and improved
information flow. In particular, coding systems are adopted to provide a numbering
system to replace verbal descriptions of items. These codes reduce the length
or complexity of the information to be recorded. A common coding system within
an organization also aids consistency in definitions and categories between projects
and among the various parties involved in a project. Common coding systems also
aid in the retrieval of historical records
of cost, productivity and duration on particular activities. Finally,
electronic data storage and retrieval operations are much more efficient with standard coding
systems.
The most widely used standard coding system
for constructed facilities is the MASTERFORMAT system developed by the Construction Specifications Institute
(CSI) of the United States and Construction Specifications of Canada.
After development of separate systems,
this combined system was originally introduced as the Uniform Construction
Index (UCI) in 1972 and was subsequently
adopted for use by numerous firms, information providers, professional
societies and trade
organizations. The
term MASTERFORMAT was introduced with the 1978 revision of the UCI codes.
MASTERFORMAT provides a standard
identification code for nearly all the elements associated with building
construction.MASTERFORMAT involves a hierarchical coding system with multiple
levels plus keyword text descriptions of each item.In the numerical coding
system, the first two digits represent one of the sixteen divisions for work; a
seventeenth division is used to code
conditions of the contract for a constructor. In the latest version of the
MASTERFORMAT, a third digit is added to
indicate a subdivision within each division. Each division is further specified
by a three digit extension indicating another
level of subdivisions. In many cases, these subdivisions are further
divided with an additional three digits to identify more specific work items or materials. For
example, the code 16-950-960, "Electrical Equipment Testing" are
defined as within Division 16 (Electrical) and Sub-Division 950 (Testing). The
keywords "Electrical Equipment Testing" is a standard description of
the activity.While MASTERFORMAT provides a very useful means of organizing and
communicating information, it has some obvious
limitations as a complete project coding system. First, more specific information
such as location of work or responsible
organization might be required for project cost control. Code extensions are
then added in addition to the digits in
the basic MASTERFORMAT codes. For example, a typical extended code might have
the following elements:
0534.02220.21.A.00.cf34
The first four digits
indicate the project for this activity; this code refers to an activity on
project number 0534. The next five digits refer to the MASTERFORMAT secondary
division; referring to Table 9-7, this activity would be 02220
"Excavating, Backfilling and Compacting." The next two digits refer
to specific activities defined within this MASTERFORMAT code; the digits 21 in
this example might refer to excavation of column footings. The next character
refers to the block or general area on the site that the activity will take
place; in this case, block A is indicated. The digits 00 could be replaced by a
code to indicate the responsible organization for the activity. Finally, the
characters cf34 refer to the particular design element number for which this excavation is intended;
in this case, column footing number 34 is intended. Thus, this activity is
to perform the excavation for column
footing number 34 in block A on the site.
4. Discuss the various factors deciding the
activity durations.
In most scheduling
procedures, each work activity has associated time duration. These durations
are used extensively in preparing a
schedule. The entire set of activities would then require at least 3 days,
since the activities follow one another directly
and require a total of 1.0 + 0.5 + 0.5 + 1.0 = 3 days. If another activity
proceeded in parallel with this sequence, the 3
day minimum duration of these four activities is unaffected. More than 3
days would be required for the sequence if there was a delay or a lag between the completion
of one activity and the start of another.
Durations and Predecessors for a Four
Activity Project Illustration
Activity
|
Predecessor
|
Duration
(Days)
|
Excavate
trench
|
----
|
1.0
|
Place
formwork
|
Excavate
trench
|
0.5
|
Place
reinforcing
|
Place
formwork
|
0.5
|
Pour
concrete
|
Place
reinforcing
|
1.0
|
All formal scheduling
procedures rely upon estimates of the durations of the various project
activities as well as the definitions of
the predecessor relationships among tasks. The variability of an activity's duration
may also be considered. Formally, the
probability distribution of an activity's duration as well as the expected or
most likely duration may be used in scheduling.
A probability distribution indicates the chance that a particular activity
duration will occur. In advance of actually
doing a particular task, we cannot be certain exactly how long the task
will require. A straightforward approach
to the estimation of activity durations
is to keep historical records of particular activities and rely on the average
durations from this experience in making
new duration estimates. Since the scope of activities are unlikely to be
identical between different projects,
unit productivity rates are typically employed for this purpose. For example,
the duration of an activity D ij such
as concrete formwork assembly might be
estimated as:
D ij =
Where A ij is the required formwork area to assemble (in
square yards), P ij is the average
productivity of a standard crew in this
task (measured in square yards per hour), and N ij is the number of crews assigned to the task.
In some organizations, unit production
time, T ij , is defined as the time
required to complete a unit of work by a standard crew
Learning phase Steady
state phase
Productivity
Time
Random factors will
also influence productivity rates and make estimation of activity durations
uncertain. For example, a scheduler will typically not know at the time of
making the initial schedule how skillful the crew and manager will be that are assigned to a particular project.
The productivity of a skilled designer may be many times that of an
unskilled engineer. In the absence of
specific knowledge, the estimator can only use average values of productivity.
5. Explain how precedence relationship among
activities are defined.
Precedence relations
between activities signify that the activities must take place in a particular
sequence.Numerous natural sequences exist for construction activities due to
requirements for structural integrity, regulations, and other technical requirements. For example,
design drawings cannot be checked before they are drawn. Diagramatically, precedence relationships can be illustrated
by a network or graph in which the activities are represented by arrows .
The arrows in Figure are called branches
or links in the activity network, while the circles marking the beginning or
end of each arrow are called nodes or
events. In this figure, links represent particular activities, while the nodes
represent milestone events.
Excavate place formwork place reinforcement pour concrete Trench
Excavate place formwork place reinforcement pour concrete Trench
Illustrative
Set of Four Activities with Precedences
More complicated precedence
relationships can also be specified. For example, one activity might not be
able to start for several days after the
completion of another activity. As a common example, concrete might have to
cure (or set) for several days before
formwork is removed. This restriction on the removal of forms activity is
called a lag between the completion of
one activity (i.e., pouring concrete in this case) and the start of another
activity (i.e., removing formwork in this
case). Many computer based scheduling programs permit the use of a variety of
precedence relationships.Three mistakes should be avoided in specifying
predecessor relationships for construction plans. First, a circle of
activity precedences will result in an
impossible plan. For example, if activity A precedes activity B, activity B
precedes activity C, and activity C
precedes activity A, then the project can never be started or completed! Figure
9-4 illustrates the resulting activity network.
Fortunately, formal scheduling methods and good computer scheduling programs will
find any such errors in the logic of the
construction plan.
A
C B
Example
of an Impossible Work Plan
Finally, it is
important to realize that different types of precedence relationships can be
defined and that each has different implications
for the schedule of activities:
Some activities have a necessary technical
or physical relationship that cannot be superseded. For example,concrete pours
cannot proceed before formwork and reinforcement are in place.
Some activities have a necessary
precedence relationship over a continuous space rather than as discrete work
task relationships. For example,
formwork may be placed in the first part of an excavation trench even as the
excavation equipment continues to work further along in the trench. Formwork
placement cannot proceed further than the excavation, but the two activities
can be started and stopped independently within this constraint.
Some "precedence relationships"
are not technically necessary but are imposed due to implicit decisions within
the construction plan.
Unit
2
1. What is the object of scheduling?.
Scheduling means putting the plan on calendar
basis. A project network shows the sequence and inters dependencies of activities, their time and their earliest and
latest completion time, but these needs to be scheduled to determine commencement and termination dates of each
activity. Using optimum resources or working within resource constraints,
it is a time table of work. A basic
distinction exists between resource oriented scheduling techniques. The project
is divided into number of
operations.
2.
List out the advantages of scheduling.
1. By studying of any
work and the many alternative methods of execution, we can choose the best
one.
2. It gives a
clear idea regarding the required men,
materials and equipments at different stages of work.
3. Resource
utilization is optimized.
4. Actual progress of
the work is monitored with the actual plan. If there is any delay, proper
remedial measures can be taken to avoid
such delays.
3.
What is the purpose of work scheduling?
The bar – chart type
work schedule provides a simplified version of the work plan, which can easily
be understood by all concerned with
planning, co – ordination, execution and control of the project.
(b) It validates the
time objectives:
A work schedule shows
the planned sequence of activities, data – wise while putting the work plan on
a calendar basis, it takes into account
reduced efficiency of resources to adverse climatic conditions and other
factors.
( c) It evaluates the implications of
scheduling constraints:
A work schedule brings
out the implications of constraints and enables preparation of a plan of work
within the frame work of these
constraints.
4. What are the steps involved in schedule
chart?
(a) Select the EST
point of activity layout on the graph, and draw a line sloping equal to its
rate of execution i.e., 1 unit per day.
(b) Plot the lowest rate slowing line and mark
its intersection with the top to foundation horizontal line.
( c ) Starting from
the point of intersection, move forward horizontally on the top line and
identify latest completion point of subsequent
activity as indicated by the set back.
5.
What are the factors affecting work scheduling?
(a) Time:
Most of the projects
carry time constraints in the form of imposed dates, these dates may include
constraints on start and completion of
activities.
(b)
Manpower:
Man power is one of the main in the successful
execution of projects. The idle labour time is paid for and the strikes
and breakdown of work are kept in view
by manpower.
(c) Materials:
Construction materials
are increasingly becoming scarce and their procurement is a time consuming
process. The schedule aids in
forecasting of materials and their timely supply determines the economics and
progress work.
6.
What is the purpose of numbering events?
i. It simplifies the identification and
description of a n activity in terms of event numbers.
ii. The activities are
coded as i- j where i and j are the event numbers as commencement and
termination of an activity.
iii. It helps in
developing identification code for computer application.
iv. It systematizes the computations of
critical path for each activity as far as possible, the number of the
proceeding event
it should be less than
that of the succeeding event.
7.
Define the following terms:
1. Critical path:
The longest path through the network is
called critical path and its length determines the minimum durations in
which the project can be completed.
2. PERT (Program Evaluation and Review
Technique):
PERT is vent oriented. It is parabolistic
model i.e., it takes into account uncertainties involved in the estimation time
of a job or an activity. It uses three
estimates of the activity time, optimistic time and pessimistic time and, most
likely time.
3. Dummy activity:
It is superimposed activity, which does
not represent any specific operation or process. It has zero duration and consumes no resources, its purpose is
twofold.
(a) To provide a logical link to maintain the
correct.
(b) To simplify the description of concurrent
activities in terms of event numbers. The dummy activity is drawn like any other activity, but with dotted lines.
8. What is the significance of critical
path?
(a) It is the longest path in the
network; however it is possible for a network to have more than one critical
path. The sum of the durations of
critical activities along the critical path determines the duration of the
project.
(b). It is the most sensitive path, any
change in duration critical activities along the critical path is bound to
effect the duration of the entire
project.
9.
Define the following terms.
1. EST (Earliest Start Time):
This is the earliest time an activity
can be started, assuming that all the activities prior to it have taken place
as early as possible.
2. LST (Latest Start Time) :
This is the latest time an activity can
start consistent, with the completion of the project in the stipulated time.
The LST of an activity is determined by
subtracting the activity duration from the LFT of succeeding event.
3. EFT (Earliest Finish Time):
It is the earliest time by which an
activity can be completed assuming that all the activities prior to it begin at
their EST.
4. LFT (Latest Finish Time):
It is the latest time by which an
activity must be completed to ensure the completion of project within the
stipulated time.
10.
What are the classifications of networks?
1. Skeleton network
2. Master network
3. Detail network
4. Summary network.
11. Define the following terms:
(a) Float:
The difference between
the latest start time and earliest start
time of an activity is called as float. Float is a measure of the amount of time by which the start of an
activity can be delayed consistent with the completion of the project on
time.
(b) Total Float:
Total float of an activity is defined
as the difference between the maximum duration of time available for the completion and duration required to carry out
that duration.
12.
What is mean by resource leveling and crashing?
Resource leveling:
The aim is reduce the peak resource
requirements and smooth out period to period assignment within a constraint on
the project duration.
Crashing:
Higher amounts of
direct activity cost would be associated with smaller activity duration times,
while longer duration time would involve
comparatively lower direct cost. Such deliberate reduction of activity times by
putting in extra effort is called
Crashing.
13.
Define the following terms:
1.
Normal cost:
Normal cost is the lowest possible
direct cost required to complete an activity.
2. Normal time:
Normal time is the maximum time
required to complete an activity at normal cost.
3.
Crash time:
Crash time is the minimum possible time
in which an activity can be completed using additional resources.
4.
Crash cost:
Crash cost is the direct cost i.e.,
anticipated in completing an activity within the crash time.
14.
Define activity cost slope.
Activity cost slope is the rate of
increase in the cost of activity per unit with a decrease in time. The cost
slope indicates the additional cost
incurred per unit of time saved in reducing the duration of an activity.
Activity Cost slope = crash cost – Normal cost .
Normal time – Crash time
SIXTEEN MARKS QUESTIONS
1.Explain Critical path method with neat
sketches.
The most widely used
scheduling technique is the critical path method (CPM) for scheduling, often
referred to as critical path scheduling.
This method calculates the minimum completion time for a project along with the
possible start and finish times for the
project activities. Indeed, many texts and managers regard critical path
scheduling as the only usable and practical
scheduling procedure. Computer programs and algorithms for critical path
scheduling are widely available and can
efficiently handle
projects with thousands of activities.
The critical path
itself represents the set or sequence of predecessor/successor activities which
will take the longest time to complete.
The duration of the critical path is the sum of the activities' durations along
the path. Thus, the critical path can be
defined as the longest possible path through the "network" of
project activities. The duration of the critical path represents
the minimum time
required to complete a project. Any delays along the critical path would imply
that additional time would be required
to complete the project.
There may be more than
one critical path among all the project activities, so completion of the entire
project could be delayed by delaying
activities along any one of the critical paths. For example, a project
consisting of two activities performed
in parallel that each require three days would have each activity critical for
a completion in three days.
Formally,
critical path scheduling assumes that a project has been divided into
activities of fixed duration and well defined predecessor relationships. A predecessor
relationship implies that one activity must come before another in the
schedule. No resource constraints other than those implied by precedence
relationships are recognized in the simplest form of critical path scheduling.
An Activity-on-Branch
Network for Critical Path Scheduling
An Activity-on-Node
Network for Critical Path Scheduling
2. Explain Activity float and schedules.
A number of different
activity schedules can be developed from the critical path scheduling procedure
described in the previous section. An
earliest time schedule would be developed by starting each activity as soon as
possible, at ES(i,j). Similarly, a
latest time schedule would delay the start of each activity as long as possible
but still finish the project in the minimum
possible time. This late schedule can be developed by setting each activity's
start time to LS(i,j).
Activities that have different early and late
start times (i.e., ES(i,j) < LS(i,j)) can be scheduled to start anytime
between ES(i,j) and LS(i,j). The concept
of float is to use part or all of this allowable range to schedule an activity
without delaying the completion of the
project. An activity that has the earliest time for its predecessor and successor
nodes differing by more than its
duration possesses a window in which it can be scheduled. That is, if E(i) +
Dij < L(j), then some float is available in
which to schedule this activity.
Float is a very valuable concept since it
represents the scheduling flexibility or "maneuvering room" available
to complete particular tasks. Activities
on the critical path do not provide any flexibility for scheduling nor leeway
in case of problems. For activities with
some float, the actual starting time might be chosen to balance workloads over
time, to correspond with material deliveries,
or to improve the project's cash flow.
3. Describe various methods of presenting
project schedules.
Communicating the
project schedule is a vital ingredient in successful project management. A good
presentation will greatly ease the
manager's problem of understanding the multitude of activities and their
inter-relationships. Moreover, numerous individuals
and parties are involved in any project, and they have to understand their
assignments. Graphical presentations of
project schedules are particularly useful since it is much easier to comprehend
a graphical display of numerous pieces of
information than to sift through a large table of numbers. Early
computer scheduling systems were particularly poor in this regard since they produced pages and pages of
numbers without aids to the manager for understanding them. It is extremely tedious to read a table of activity
numbers, durations, schedule times, and floats and thereby gain an understanding and appreciation of a project
schedule. In practice, producing diagrams manually has been a common prescription to the lack of automated
drafting facilities. Indeed, it has been common to use computer programs to
perform critical path scheduling and
then to produce bar charts of detailed activity schedules and resource
assignments manually.
With the availability
of computer graphics, the cost and effort of producing graphical presentations
has been significantly reduced and the
production of presentation aids can be automated. Network diagrams for projects have already
been introduced. These diagrams provide a powerful visualization of the precedences and relationships among the
various project activities. They are a basic means of communicating a project
plan among the participating planners
and project monitors. Project planning is often conducted by producing
network representations of greater and
greater refinement until the plan is satisfactory.
An Example Bar Chart
for a Nine Activity Project
Bar charts are
particularly helpful for communicating the current state and schedule of
activities on a project. As such, they have
found wide acceptance as a project representation tool in the field. For
planning purposes, bar charts are not as useful
since they do not indicate the precedence relationships among
activities. Thus, a planner must remember or record separately that a change in one activity's
schedule may require changes to successor activities. There have been
various schemes for mechanically linking
activity bars to represent precedences, but it is now easier to use computer
based tools to represent such
relationships.
5.
Explain Scheduling with Resource Constraints and Precedence
Two problems arise in
developing a resource constrained project schedule. First, it is not necessarily
the case that a critical path schedule
is feasible. Because one or more resources might be needed by numerous activities,
it can easily be the case that the
shortest project duration identified by the critical path scheduling
calculation is impossible. The difficulty arises because critical path scheduling assumes that
no resource availability problems or bottlenecks will arise. Finding a
feasible or possible schedule is the
first problem in resource constrained scheduling. Of course, there may be a
numerous possible schedules which
conform with time and resource constraints. As a second problem, it is also
desirable to determine schedules which
have low costs or, ideally, the lowest cost.
Numerous heuristic methods have been suggested for resource constrained
scheduling. Many begin from critical path
schedules which are modified in light of the resource constraints.
Others begin in the opposite fashion by introducing resource constraints and then imposing
precedence constraints on the activities. Still others begin with a ranking
or classification of activities into
priority groups for special attention in scheduling.One type of heuristic may
be better than another for different
types of problems. Certainly, projects in which only an occasional resource
constraint exists might be best
scheduled starting from a critical path schedule. At the other extreme,
projects with numerous important resource
constraints might be best scheduled by considering critical resources
first. A mixed approach would be to proceed
simultaneously considering precedence and resource constraints.
A simple
modification to critical path scheduling has been shown to be effective for a
number of scheduling problems and is simple
to implement. For this heuristic procedure, critical path scheduling is applied
initially. The result is the familiar set of
possible early and late start times for each activity. Scheduling each
activity to begin at its earliest possible start time may result in more than one activity requiring a
particular resource at the same time. Hence, the initial schedule may not
be feasible. The heuristic proceeds by
identifying cases in which activities compete for a resource and selecting one
activity to proceed. The start time of
other activities are then shifted later in time. A simple rule for choosing
which activity has priority is to select
the activity with the earliest CPM late start time (calculated as LS(i,j) =
L(j)-Dij) among those activities which are
both feasible (in that all their precedence requirements are satisfied)
and competing for the resource. This decision rule is applied from the start of the project until
the end for each type of resource in turn.
UNIT-III
1. List out any 5 indirect cost.
Temporary utility
,Cleaning ,Unloading ,Ware housing ,Work
shop
2. What is meant by Contigencies?
Contigency is a cushion of cost to deal
with uncertainities.Few factors resulting in contigencies are minor design changes,under estimate of cost,lack of
experience,unanticipated price changes,safety problems etc.
3. What is meant by Budget?
Budget is an estimate of cost planned
to be spent to complete a particular activity.
4.
What are the types of cost flow?
1) Cash Inflow
2) Cash outflow
5.
What is meant by Cost Forecasting?
Cost Forecasting is the requirement of
cost to continue with the project at the desired speed.
6. What is meant by Cash Flow control?
Cash Flow control is the additional
planning required to arrange the cash to meet the demand for the funds.
7. What are the sources of cash inflow?
1. Sales of goods,
2. Investment from the
owner,
3. Debt financing
(loan),
4. Sales of
shares
8. What are the sources of cash outflow?
1. Purchase of shares,
2. Payment of dues on
loan,
3. Payment of bills,
4.Taxes
9. List out the cost control problems
Equipment rate variance
Equipment operating variance
Labour
rate variance
Material wastages
Equipment variance
Other common reasons
10.
What are the project cost budget monitoring parameters?
Budget cost of work Scheduled(BCWS)
Budget cost of work
Performed(BCWP)
Actual cost of work Performed
(ACWP)
11.
What are the methods of measuring progress of work?
Ratio method
Repetitive type of work progress
Non Repetitive complexwork
progress
Start/Finish method
12.
What are the types of accounting?
1) Financial Accounting
2) Cost Accounting
13.
What are the types of Assets?
1) Current Assets
2) Liquid Assets
3) Fixed Assets
4) Intangible Assets
14.
What are the types of Liabilities?
1) Current Liabilities
2) Fixed Liabilities
3)
15.
Give the hourly Productivity forecasting formula.
C f =w*h f *u t
Where,
C f =Total units of work
W=Total units of work
h f =Time Per unit
u t =Cost per unit time
16
MARKS QUESTIONS
1. Explain Forecasting for Activity Cost
Control
For the purpose of
project management and control, it is not sufficient to consider only the past
record of costs and revenues incurred in
a project. Good managers should focus upon future revenues, future costs and
technical problems. For this purpose,
traditional financial accounting schemes are not adequate to reflect the
dynamic nature of a project. Accounts typically
focus on recording routine costs and past expenditures associated with
activities. Generally, past expenditures
represent sunk costs that cannot be altered in the future and may or may
not be relevant in the future. For example, after the completion of some activity, it may be
discovered that some quality flaw renders the work useless. Unfortunately,
the resources expended on the flawed
construction will generally be sunk and cannot be recovered for
re-construction (although it may be
possible to change the burden of who pays for these resources by financial
withholding or charges; owners will
typically attempt to have constructors or designers pay for changes due to quality
flaws). Since financial accounts are
historical in nature, some means of forecasting or projecting the future course
of a project is essential for management
control.
Budgeted Cost
The budgeted cost is derived from the detailed
cost estimate prepared at the start of the project. The factors of cost
would be referenced by cost account and
by a prose description.
• Estimated total cost
The estimated or forecast total cost in each
category is the current best estimate of costs based on progress and any changes since the budget was formed.
Estimated total costs are the sum of cost to date, commitments and exposure.
Methods
for estimating total costs are described below.
Cost
Committed and Cost Exposure!!
Estimated cost to completion in each category
in divided into firm commitments and estimated additional cost or
exposure. Commitments may represent
material orders or subcontracts for which firm dollar amounts have been
committed.
Cost to Date
The actual cost incurred to date is recorded
in column 6 and can be derived from the financial record keeping accounts.
Over or (Under)
A final column in
Table 12-4 indicates the amount over or under the budget for each category. This
column is an indicator of the extent of
variance from the project budget; items with unusually large overruns would represent
a particular managerial concern. Note
that variance is used in the terminology of project control to indicate a difference
between budgeted and actual
expenditures. The term is defined and used quite differently in statistics or
mathematical analysis.
2. Explain the types of Accounting systems.
The cost accounts
described in the previous sections provide only one of the various components
in a financial accounting system. Before
further discussing the use of cost accounts in project control, the relationship
of project and financial accounting
deserves mention. Accounting information is generally used for three distinct
purposes:
Internal reporting to project managers for
day-to-day planning, monitoring and control.
Internal reporting to managers for aiding strategic
planning.
External reporting to owners, government,
regulators and other outside parties.
External reports are
constrained to particular forms and procedures by contractual reporting
requirements or by generally accepted
accounting practices. Preparation of such external reports is referred to as
financial accounting. In contrast, cost or
managerial accounting is intended to aid internal managers in their
responsibilities of planning, monitoring and control. Project costs are always included in the
system of financial accounts associated with an organization. At the heart of
this system, all expense transactions
are recorded in a general ledger. The general ledger of accounts forms the
basis for management reports on
particular projects as well as the financial accounts for an entire organization.
Other components of a financial
accounting system include:
The accounts payable journal is intended
to provide records of bills received from vendors, material suppliers, subcontractors and other outside parties.
Invoices of charges are recorded in this system as are checks issued in payment. Charges to individual cost accounts
are relayed or posted to the General Ledger.
Accounts receivable journal provide the
opposite function to that of accounts payable. In this journal, billings
to clients are recorded as well as
receipts. Revenues received are relayed to the general ledger.
Job cost ledgers summarize the charges
associated with particular projects, arranged in the various cost accounts used for the project budget.
Inventory records are maintained to
identify the amount of materials available at any time.
In traditional
bookkeeping systems, day to day transactions are first recorded in journals. With
double-entry bookkeeping, each
transaction is recorded as both a debit and a credit to particular accounts in
the ledger. For example, payment of a supplier's
bill represents a debit or increase to a project cost account and a credit or
reduction to the company's cash account.
Periodically, the transaction information is summarized and transferred to
ledger accounts. This process is called posting,
and may be done instantaneously or daily in computerized systems.
In reviewing
accounting information, the concepts of flows and stocks should be kept in mind.
Daily transactions typically reflect
flows of dollar amounts entering or leaving the organization. Similarly, use or
receipt of particular materials represent
flows from or to inventory. An account balance represents the stock or
cumulative amount of funds resulting from these
daily flows. Information on both flows and stocks are needed to give an
accurate view of an organization's state. In addition, forecasts of future changes are needed for
effective management.
3. Explain cash flow control.
Project managers also
are involved with assessment of the overall status of the project, including
the status of activities, financing,
payments and receipts. These components include costs incurred (as described
above), billings and receipts for billings
to owners (for contractors), payable amounts to suppliers and contractors,
financing plan cash flows (for bonds or other
financial instruments), etc. .
In this case, costs
are not divided into functional categories , such as labor, material, or equipment.
Thus, the aggregation of different kinds
of cost exposure or cost commitment has not been performed. The elements include:
•Costs
This is a summary of charges as reflected by
the job cost accounts, including expenditures and estimated costs.
•Billings
This row summarizes the state of cash flows
with respect to the owner of the facility; this row would not be included
for reports to owners.
•Payables
The Payables row summarizes the amount owed by
the contractor to material suppliers, labor or sub-contractors.
•Receivables
This row summarizes the cash flow of receipts
from the owner. Note that the actual receipts from the owner may differ from the amounts billed due to delayed
payments or retainage on the part of the owner.
•Cash Position
This row summarizes
the cash position of the project as if all expenses and receipts for the project
were combined in a single account. Each
of the rows shown in Table 12-8 would be derived from different sets of financial
accounts. Additional reports could be
prepared on the financing cash flows for bonds or
4. Explain Schedule control
Construction typically
involves a deadline for work completion, so contractual agreements will force
attention to schedules. More generally,
delays in construction represent additional costs due to late facility
occupancy or other factors. Just as costs
incurred are compared to budgeted costs, actual activity durations may
be compared to expected durations. In this process, forecasting the time to complete particular
activities may be required.
The methods used for forecasting completion
times of activities are directly analogous to those used for cost forecasting.
For example, a typical
estimating formula might be:
Where D
f is the forecast duration, W is the
amount of work, and h t is the observed
productivity to time t. As with cost control,
it is important to devise efficient and cost effective methods for gathering
information on actual project accomplishments.
Generally, observations of work completed are made by inspectors and project
managers and then work completed is
estimated. Once estimates of work complete and time expended on particular
activities is available, deviations from
the original duration estimate can be estimated. This figure is constructed by summing up the
percentage of each activity which is complete at different points in time;
this summation can be weighted by the
magnitude of effort associated with each activity. In Figure, the project was
ahead of the original schedule for a
period including point A, but is now late at point B by an amount equal to the
horizontal distance between the planned
progress and the actual progress observed to date.
Illustration of
Planned versus Actual Progress over Time on a Project
Schedule adherence and the current status of a
project can also be represented on geometric models of a facility. In
evaluating schedule progress, it is important to bear in mind that some
activities possess float or scheduling leeway, whereas delays in activities on
the critical path will cause project delays. In particular, the delay in
planned progress at time t may be soaked up in activities' float (thereby
causing no overall delay in the project completion) or may cause a project delay. As a result of this ambiguity, it is
preferable to update the project schedule to devise an accurate portrayal of
the schedule adherence. After applying a
scheduling algorithm, a new project schedule can be obtained.
Illustration of
Planned versus Actual Expenditures on a Project
5. Explain the Project budget.
For cost control on a
project, the construction plan and the associated cash flow estimates can
provide the baseline reference for
subsequent project monitoring and control. For schedules, progress on
individual activities and the achievement
of milestone completions can be compared with the project schedule to monitor
the progress of activities. Contract and
job specifications provide the criteria by which to assess and assure the
required quality of construction. The final
or detailed cost estimate provides a baseline for the assessment of financial
performance during the project. To the extent
that costs are within the detailed cost estimate, then the project is thought
to be under financial control. Overruns in
particular cost categories signal the possibility of problems and give
an indication of exactly what problems are being encountered. Expense oriented construction
planning and control focuses upon the categories included in the final
cost estimation. This focus is
particular relevant for projects with few activities and considerable repetition
such as grading and paving
roadways.
For control and monitoring purposes, the
original detailed cost estimate is typically converted to a project budget, and
the project budget is used subsequently
as a guide for management. Specific items in the detailed cost estimate become
job cost elements. Expenses incurred
during the course of a project are recorded in specific job cost accounts to be
compared with the original cost
estimates in each category. Thus, individual job cost accounts generally represent
the basic unit for cost control.
Alternatively, job cost accounts may be
disaggregated or divided into work elements which are related both to
particular scheduled activities and to
particular cost account. In addition to cost amounts, information on material
quantities and labor inputs within each
job account is also typically retained in the project budget. With this information,
actual materials usage and labor
employed can be compared to the expected requirements. As a result, cost
overruns or savings on particular items can
be identified as due to changes in unit prices, labor productivity or in the
amount of material consumed.
The number of cost
accounts associated with a particular project can vary considerably. For
constructors, on the order of four
hundred separate cost accounts might be used on a small project. These accounts record all the transactions
associated with a project. Thus,
separate accounts might exist for different types of materials, equipment use,
payroll, project office, etc. Both
physical and non-physical resources are represented, including overhead items
such as computer use or interest charges.
No comments:
Post a Comment